Re: Material status does not allow a planned independent requir/Queue

$
0
0

MM,

Hmm.  How were you solving the problem when you had 10-20 of these?

 

Anyhow, it sounds like you are generating this message when you release the demand plan to ECC.

 

Check your material masters in ECC.  Change the material status and/or material status validity dates as necessary.  There is a material status in the Basic 1 tab, and a plant-specific material status in the MRP1 tab.

 

Best Regards,

DB49.